Application / booking money |
10% + GST |
Within 15 days from execution of agreement |
10% + GST |
On completion of pilling work of respective block |
10% + GST |
On completion of basement of respective block |
7% + GST |
On casting of 1st floor slab of respective block |
7% + GST |
On casting of 5th floor slab of respective block |
7% + GST |
On casting of 9th floor slab of respective block |
7% + GST |
On casting of roof slab of respective block |
7% + GST |
On commencement of brick work of respective block |
7% + GST |
On commencement of flooring of respective block |
6% + GST |
On commencement of lift installation of respective block |
6% + GST |
On commencement of outside paint of respective block |
6% + GST |
On possession of respective block |
10% + GST |